Unprecedented rainfall during February and March has caused a short delay to the road resurfacing works along Llantrisant Road and Heol Isaf, which can only be successfully completed during dry weather.
The necessary traffic management for the completion of the new, four-way signalised junction in place of the existing Heol Isaf roundabout can only be put in place once the resurfacing work on Heol Isaf is complete, so the start date for this section of work has changed.
Weather-dependant, this traffic management is expected to be in place towards the end of next week commencing 16 March. Exact dates will be communicated here, and on our Twitter channel @plasdwr, once confirmed.
This change is not expected to impact the overall finish time for the junction works, which are still due for completion in the summer.
*Please note all timescales are subject to change.