Following reports that the 3-way traffic lights have caused long queues through Radyr, a longer sequence time has been allowed for Heol Isaf.
Our contractors are continuing to monitor traffic flow, and will manage sequencing to keep traffic moving as quickly as possible.
3 people will remain on site until 9pm, after which the lights will be triggered by traffic rather than timed.
The drainage work will continue until 7pm tonight, then on Saturday and Sunday, to complete the pipework installation. If no complications arise, the resurfacing works should be completed during the early part of Monday so we can remove the traffic lights asap.